The $52 MOV penalty on the Vendor C line is the part I'd have missed. Per-line MIN() feels rigorous, but it quietly treats every line as its own PO. Stepping 90 up to 100 pieces to catch the price break is also a nice reminder that the cheapest quantity is not always the quantity you need. One thing worth adding is lead time: a consolidated PO on cut-tape may ship slower than a split one, and for small builds that delay can cost more than the cash saved. Do you plan to let buyers weight delivery date next to cash outlay?